Harrison Community Hospital

Medical Construction
in Cadiz, OH

Grae-Con performed two major renovations and addition projects for Harrison Community Hospital, in addition to numerous maintenance projects.

The Emergency Room and Cardiopulmonary Addition was completed in 1996. The project consisted of the construction of a new emergency room in the rear of the existing hospital. The project was completed in seven months. Grae-Con served as General Contractor and Construction Manager for the project.

The Pharmacy and Dining Addition was completed in 2001. This project featured a new cafeteria that doubled as a restaurant to the public and a new pharmacy. This project was completed in eight months. Grae-Con served as General Contractor and Construction Manager for the project.